CONSTRUCTION UPDATE

HYDE PARK PLACE - 248 UNLEY ROAD, HYDE PARK

 

LIVE FROM THE SITE

 

JULY 2020
The latest update from the site is now available.

July has seen the site team powering through from Level Two to Level Three within the month due to lots of hard work and plenty of dry weather.

First fix works continue on lower levels and steel wall framing has now commenced.

 

Citify - Hyde Park - August 2020

 

 

JUNE 2020
The latest update from the site is now available.

June has seen up complete Level 1 slab (reinforcing to partial transfer and slab pour), all Level 1 precast walls, all structural steel to support Level 2 floors,
and 80% of Level 2 hollowcare floor plans have been landed.

We are so close to commencing the final concrete slab pour and ticking off Level 2 as another successful phase.

 

Citify - Hyde Park - July 2020

 

 

MAY 2020
The latest update from the site is now available.

Plenty of milestones achieved over the last month at Hyde Park Place.
Below, in just 43 seconds, you'll see how fast our team worked together to accomplish:
 
- Poured & cured the ground floor concrete slab
- Landed ground floor precast walls
- Formed up & poured ground floor columns
- Installed first floor precast hollowcore floor planks
- Built first floor formwork & reinforcing
- Commenced basement first fix services
 
There are no signs of slowing down at Hyde Park Place!

 

Citify - Hyde Park - June 2020

 

 

APRIL 2020
The latest update from the site is now available.

Last month saw us pour ground floor columns, land precast panels and form up the rest of the ground floor slab,
which includes formwork, reinforcing and services.

Not only this, but structural steel beams and supports for the first floor slab were craned into place late last week.
 
 
Citify - Hyde Park - May 2020

 

 

MARCH 2020
The latest update from the site is now available.

The basement works are all completed. The focus now moves to the Ground Floor commercial areas.

 

Citify - Hyde Park - April 2020

 

 

 

FEBRUARY 2020
The latest update from the site is now available.

Nearly all pad footings and columns under the apartment building are formed up, reinforced and poured with concrete.

Very soon, the basement will no longer be visible.

 

Citify - Hyde Park - March 2020

 

 

 

JANUARY 2020
The latest update from the site is now available.

January sees a short month due to holidays and some very hot weather, but the site team and trades have been busy throughout!

 

 

Citify - Hyde Park - February 2020

 

 

DECEMBER 2019
The latest update from the site is now available.

Construction at the site was full steam ahead over the Christmas period.
The basement is now fully excavated.

 

Citify - Hyde Park - December 2019

 

 

NOVEMBER 2019
The latest update from the site is now available.

 

Citify - Hyde Park Place - December 2019

 

 

OCTOBER 2019
The latest update from the site is now available.

Construction works are progressing through the basement retaining works.

Citify - Hyde Park Place - November 2019

 

DEMOLITION WORKS
Demolition works for the existing structures on the site commenced in August 2019.
Below you can view the latest update from the site.

  • Hyde Park Place - Demolition Works, Sep 2019