OCTOBER 2021
The latest update from the site is now available.
OCTOBER 2020
The latest update from the site is now available.
September has seen the site team turn around over an entire floor.
Work is currently on schedule and fit out works for framing, plumbing, electrical and fire services continue on the lower levels internally.
JULY 2020
The latest update from the site is now available.
July has seen the site team powering through from Level Two to Level Three within the month due to lots of hard work and plenty of dry weather.
First fix works continue on lower levels and steel wall framing has now commenced.
JUNE 2020
The latest update from the site is now available.
June has seen up complete Level 1 slab (reinforcing to partial transfer and slab pour), all Level 1 precast walls, all structural steel to support Level 2 floors,
and 80% of Level 2 hollowcare floor plans have been landed.
We are so close to commencing the final concrete slab pour and ticking off Level 2 as another successful phase.
MAY 2020
The latest update from the site is now available.
APRIL 2020
The latest update from the site is now available.
MARCH 2020
The latest update from the site is now available.
The basement works are all completed. The focus now moves to the Ground Floor commercial areas.
FEBRUARY 2020
The latest update from the site is now available.
Nearly all pad footings and columns under the apartment building are formed up, reinforced and poured with concrete.
Very soon, the basement will no longer be visible.
JANUARY 2020
The latest update from the site is now available.
January sees a short month due to holidays and some very hot weather, but the site team and trades have been busy throughout!
DECEMBER 2019
The latest update from the site is now available.
Construction at the site was full steam ahead over the Christmas period.
The basement is now fully excavated.
NOVEMBER 2019
The latest update from the site is now available.
OCTOBER 2019
The latest update from the site is now available.
Construction works are progressing through the basement retaining works.
DEMOLITION WORKS
Demolition works for the existing structures on the site commenced in August 2019.
Below you can view the latest update from the site.